Last updated: November 2026 · By ON Design & Remodeling, a licensed design-build contractor in San Jose (CSLB #1080660)
Short answer: In San Jose you get an ADU permit by completing the city’s ADU Universal Checklist, preparing a full plan set, applying on SJPermits.org, uploading your plans to SJePlans, going through prescreen, plan review and issuance review, and then building with inspections. According to the City of San José, the first round of building review typically takes 20 business days. If you use one of the city’s preapproved ADU plans and your site documents are complete, the permit may be issued the same day as your plan review meeting. ADUs under 751 sq ft do not pay school or parkland impact fees.
The 6 steps to an ADU permit in San Jose
These are the steps the City of San José publishes on its ADU Project Process page, explained in plain English.
Step 1: Check whether your lot qualifies (ADU Universal Checklist)
The city’s ADU Universal Checklist covers which lots qualify, setbacks, height, and fire requirements. Complete it before you pay for design. If you want feedback from a planner, you can call the Planning Division at 408-535-3555 or email [email protected] for basic questions (no plan review). For project-specific feedback, you can request a preliminary virtual meeting through the ADU Ally team. The city bills it at the Planning Division’s hourly rate (listed as $398/hour, 30-minute minimum).
Step 2: Prepare your ADU plans
The city recommends working with an experienced professional. Your design should follow Bulletin 211 (ADU Building Plan Requirements), the ADU Inspection Checklist, the Fire Requirements for ADUs, and, for a junior ADU, Building Division Note 34.
Step 3: Start the online application
Use the city’s Application Wizard, then create an account on SJPermits.org. You will enter the address and scope and name an “ePlan Applicant”, the person who uploads documents and answers reviewer comments. When ON Design & Remodeling manages a project, our team handles this role.
Step 4: Upload a complete submittal package to SJePlans
The city states it will not process inaccurate or incomplete plans. The package includes:
- Plans per Bulletin #211 and the Bulletin #213 Inspection Checklist for ADUs
- Title 24 energy calculations and the CALGreen checklist (in the plan set)
- A geotechnical report, if your site needs one
- A water flow letter from your water company for the hydrant closest to your lot
- Form 302 Address Assignment Request (every ADU gets its own address)
- Form 312 ADU Property Owner Declaration (for a junior ADU, Form 313 JADU Deed Restriction Agreement, which needs a wet signature)
Tip: The city says projects are often delayed because the water flow letter is missing. Request it on day one. San Jose is served by San Jose Water, Great Oaks Water, or San Jose Municipal Water, depending on your address.
Step 5: Prescreen, plan review, and issuance
- Prescreen: a city Permit Specialist confirms the package is complete and invoices the initial plan review fee.
- Plan review: reviewers post comments in SJePlans and you resubmit corrected plans. The city says the first round typically takes 20 business days. Resubmitting without fixing every comment adds more cycles.
- Issuance review: after approval, you pay the remaining plan review and inspection fees and any school and parkland fees. Then the permit is issued in SJePlans.
Step 6: Build and pass inspections
Construction starts once the permit is issued. Your contractor schedules inspections and shows the inspector the Bulletin #213 checklist, the approved plans, and the permit card. Before the final inspection, the Construction and Demolition Diversion sign-off has to be done. When the final passes, the ADU is ready to live in or rent.
Ready to build? Learn about our ADU construction services or see our San Jose remodeling and ADU page.
Planning an ADU in San Jose?
ON Design & Remodeling handles site review, design, permits, and construction under one contract.
Or call (800) 992-5997

Preapproved ADU plans: the fastest route in San Jose
San Jose keeps a list of preapproved ADU plans, standard designs the city has already reviewed. You still submit site-specific documents (where the unit sits, utilities, setbacks). The city says that if those documents are accurate and complete, the permit may be issued the same day as the plan review meeting. To qualify for same-day issuance:
- The lot is zoned residential and already has a single-family home or duplex.
- The lot is not in a geohazard, landslide, flood, or Wildland-Urban Interface (WUI) zone.
Changes to a preapproved plan send the project back into standard review. A custom design takes longer to permit, but it can fit an unusual lot or a specific layout better.
Fire requirements that often surprise San Jose homeowners
From the city’s ADU FAQ:
- If the main house has fire sprinklers, the ADU needs them too.
- An attached ADU over 500 sq ft, where the house and ADU together are over 3,600 sq ft, means the whole house and ADU must be sprinklered.
- Every part of the ADU should be within 150 feet of the street curb along a clear path at least 4 feet wide. Otherwise a fire variance may be required.
- All exterior walls should be within 600 feet of a fire hydrant. Otherwise a fire variance may be required.
- The nearest hydrant should deliver 1,000 gpm at 20 psi. If it doesn’t, fire staff decide whether extra safety measures are needed.
San Jose ADU fees: what you pay, and what you can avoid
- Building permit fees depend on the ADU’s size. The city offers a Building Fee Estimator.
- School and parkland impact fees do not apply to ADUs under 751 sq ft. Parkland fees are based on interior square footage, so show interior and exterior dimensions clearly on the plans.
- Some sites also need a geological hazard clearance, a tree removal permit, a fire variance, or a grading permit or exemption.
- Property taxes go up based on the value the ADU adds (see the Santa Clara County Assessor).

How much does an ADU cost in San Jose?
Our Bay Area ADU cost guide gives typical Bay Area ranges: a detached ADU about $280K–$600K+, an attached ADU about $160K–$350K, a garage-conversion ADU about $200K–$320K, and a junior ADU (JADU) about $65K–$130K. Your price depends on size, site work, utilities, permits, and finishes. The only way to get a real number is a site-specific estimate.
Other San Jose ADU rules worth knowing
- Separate address: every ADU and JADU gets an address during permitting.
- Separate meter: PG&E requires ADUs to have their own electric meter. JADUs do not.
- Gas or all-electric: the city has paused enforcement of its natural gas ban, so either is allowed. The city encourages all-electric.
- Renting: you can rent the house and the ADU to different tenants. The minimum rental term is 30 days, including Airbnb.
- Selling the ADU separately requires a condominium conversion.
- New house + ADU together is allowed. The house must pass final inspection before the ADU’s final.
Frequently asked questions
How long does it take to get an ADU permit in San Jose?
The City of San José says the first round of building review typically takes 20 business days. Total time depends on how many correction cycles you need. With a preapproved plan and complete site documents, the permit may be issued the same day as the plan review meeting.
Do I pay impact fees on an ADU in San Jose?
School and parkland impact fees do not apply to ADUs under 751 sq ft. ADUs of 751 sq ft or more may owe them. Contact your school district about its fees.
Does a San Jose ADU need its own electric meter?
Yes. PG&E requires ADUs to have their own utility meter. Junior ADUs (JADUs) are not separate units and do not need one.
Can I rent out my ADU on Airbnb in San Jose?
Only for stays of at least 30 days. State law sets 30 days as the minimum rental term for ADUs, including Airbnb.
What is the most common cause of ADU permit delays in San Jose?
The city points to missing water flow letters and incomplete or uncorrected plans. Request the hydrant flow letter early, and answer every reviewer comment before you resubmit.
Who can manage the ADU permit for me?
The city recommends using an experienced professional and advises having the vendor or contractor pull the permit. ON Design & Remodeling designs ADUs, prepares and submits the plans, works with the city through approval, and builds the unit as a licensed general contractor (CSLB #1080660).
Planning an ADU in San Jose?
ON Design & Remodeling is a design-build contractor at 1762 Technology Dr., Suite 226, San Jose. We handle ADUs from site review and design through permits, construction, and final inspection. Call (800) 992-5997 or book a free consultation.
Planning an ADU in San Jose?
Book a free consultation and we will walk your lot, the city’s checklist, and a realistic path to a permit.
Or call (800) 992-5997